PROJECT EXPERIENCE
home
PROJECT EXPERIENCE
Popular Question
1. Contracting contract / paving of Al Doctors Street in Khor Al Zubair
COST OF THE PROJECT: 85,000 $
YEAR: 2005
USERS: Basra province
2. Rehabilitation and maintenance of surfaces in the new Marbad area and apartments
COST OF THE PROJECT: 51,310,000 IQD
YEAR: 2004
USERS: South Oil Company
3. Create 10 floors in Al Marbad
COST OF THE PROJECT: 432,823,000 IQD
YEAR: 2004
USERS: South Oil Company
4. Reconstruction of Al-Shuwaili Mosque
COST OF THE PROJECT: 199,000 $
YEAR: 2005
USERS: Basra province
5. The new steam boiler project from Nebraska Boiler / The work includes all civil works and pouring more than 1500 cubic meters of reinforced concrete for the plant equipment bases and implementing the entire control building with the finishing of the control room and engine operating room
COST OF THE PROJECT: 1,450,000 $
YEAR: 2012
USERS: joint venture
6. Boiler water treatment project with a capacity of 300 cubic meters / hour, affiliated to Al-Majd Electromechanical Company. The entire architecture and underground water basins of 4 meters, all of them, bases and quantities of more than 1,400 cubic meters of reinforced concrete and installation. with each other
COST OF THE PROJECT: 845,000 $
YEAR: 20015
USERS: joint venture
7. The company has worked over the past years since its establishment by taking secondary contracts in the construction, electrical and mechanical disciplines, and supplying all construction materials, equipment and machinery.
COST OF THE PROJECT: More than 1,000,000 $
YEAR: 2007-2018
USERS: joint venture/Subcontractor
8. The company worked for the years 2016, 2017, 2018, 2019 and 2020, by taking secondary contracts to implement the well pads in the Zubair field and the Rumaila field in Basra, and the works of preparing construction materials and earthworks, and supplying all equipment and machinery.
COST OF THE PROJECT: More than 2,000,000 $
YEAR: 2016- 2017- 2018 -2019 -2020
USERS: